GENERAL INSTALLATION INFORMATION
• All power must be turned off prior to wiring, installation or service.
• More than one disconnect may be required to de-energize power to the LP8.
• External circuit protection to the LP8 is required (for example, circuit breaker).
• Installation shall be in accordance with all applicable regulations, wiring practices, and
codes.
• Care should be taken to separate high voltage power from low voltage (Class 2) control
wiring.
• Do not energize wiring until the unit is fully assembled and connected circuits have been
tested and found to be free of electrical shorts.
WARNING: TURN THE POWER OFF AT THE
CIRCUIT BREAKER BEFORE WIRING.
Status LEDs (7)
Solid Green (4)
Power LEDs (2)
Solid Green
Solid Green (2)
Blinking Blue (1)
Relay Driver (RD)
boards (2)
Flashing Blue
(at DS6)
Power Supply
(PS) board
C8 (motherboard)
Blinking Amber on RD board
(at DS7) = trouble condition
Flashing
Blue
LEDs (2)
= normal
operation
Group Switch Card (optional)
Blinking
Amber
LEDs (2)
= trouble
condition
POWER UP AND TEST
1. Power up the panel.
2. Complete the tests in the table.
3. Upon completing and passing all tests, power down the panel.
4. Install, connect, and test low voltage devices, contactors and loads to the panel per the
instructions referenced in the Resources section below.
5. Program the clock per your application requirements and record relay schedules and
scenario information on the Programming Record Sheet.
WARNING: IMPROPER INSTALLATION OR
CONNECTION OF THE LP8 MAY RESULT
IN SERIOUS PERSONAL INJURY AND/OR
DAMAGE TO THE LP8 AND OTHER DEVICES..